All work

Mytheresa, early 2023

Leading production readiness for a shop migration

Mytheresa moved its whole shop to a new system. I led production readiness for about six months, across about 20 teams, from workflow mapping to the pilot launch.

Role
Led production readiness
Timeline
About six months, early 2023
Team
About 20 business teams, engineering, experts and POs
Scope
The full shop system and every team workflow on it

The problem

About 20 teams depended on a shop system that was about to be replaced, and nobody had written down how they used it.

Workflows nobody had written down

Every team relied on daily routines in the old system that existed only in people's heads.

Records to line up

Customer records had to match the new system before launch.

A clear launch bar

The final month had to separate real launch blockers from everything else.

What I did

Turned workflows into acceptance criteria

Every team mapped its daily workflows into acceptance criteria and UAT cases, tracked in 12 weekly check-ins with experts and POs.

Fixed the data match with engineering

We matched customer records on another unique field instead of the legacy ID, so records lined up before launch.

Triaged by revenue impact

I ranked the open bugs by revenue impact, effort and launch criticality. All 25 launch blockers were cleared in 3 weeks.

The call

  • Launch everywhere at once

    One cut-over, but every channel exposed to the same risks.

  • What we did

    Pilot in the Netherlands first

    A low-risk channel to prove the system before scaling.

Results

The pilot went live on schedule with every launch blocker cleared.

6 monthsof production readiness I led
~20teams made launch-ready
1pilot market first, on schedule
25launch blockers cleared in 3 weeks

What worked

  • Writing each team's workflows down as acceptance criteria turned unknowns into testable cases.
  • Triage by revenue impact focused the last month on what could actually block launch.

What didn't

  • Testing ran alongside the build, which made the final month tight.

What I'd do differently

I'd start the workflow mapping before the build rather than alongside it, so testing could begin earlier.

Working on search, discovery or product data? Let's talk.